B ) SOCIO ECONOMIC AND CULTURAL ENVIRONMENT
The location of the circus headquarters, being near to a metropol like Istanbul, creates an advantage in recruiting qualified administrative and technical personnel. In addition, overhead personnel can be employed from the surroundings of headquarters. For different types of shows, show groups or families can be searched in all over the world. Famous groups or individuals can be contracted ofcourse with high transfer cost. However, these transfer costs should not be seen as financial burdens since they will bring out the circus brand to a more prestigious status while increasing the customer demand, and hence the profit margin. Moreover, we consider transferring show people from Far East Countries or Russia which would provide cheaper work force.
E ) TRAINING PLAN
In accordance with the implementation plan, progressive approach would be taken in the development of the circus show. At the first stage, constructing of headquarters, infant animals would be purchased and the respective trainers will be hired. These trainers will train both our personnel (to be recruited as future animal trainers and show personnel) and the purchased animals. The estimated training would be 18-26 months ( source: The Great Circus Parade ). During this training period small performances would be given in response to special requests or occasions such as festivals or fairs with hired people such as band, clowns, acrobats…etc. by using the circus train.
F ) COST ESTIMATES
Cost related to human factors can be analysed under three main headings which are:
1. Recruitment Cost: These costs will be incurred before the actual employment of the personnel and include advertisement costs, transfers paid for high skilled employees, job interview costs including demo shows
2. Monthly Salaries: The salaries will be determined according to the importance of the jobs and skills and experience of the employee in the related field and also this cost includes insurance costs.
3. Training Costs: The required training for the personnel should be provided by outside trainers in the initialization phase. In the second phase of the implementation of the project, our trained personnel will train our animals and novices so we will expect the decrease in training cost in the future.
The mentioned costs will differ according to the department and position of the employee. The estimated costs per employee are summarized in Table I for initialization phase and TABLE II for future.
PERSONNEL | Number | Recruitment Cost/man | Monthly Salaries | Training Cost | TOTAL COST/month |
Administrative | 10 | $2000 | $700 | ----------- | $700 |
Technical | 7 | $200 | $300 | $100 | $400 |
Show | 25 | $300 | $200 | $300 | $500 |
Overhead | 7 | $100 | $250 | $50 | $300 |
Training | 5 | $8000 | $1200 | ------------ | $1200 |
$ 69,000 Recruitment Cost
$ 30,400 Monthly Personnel Expenses
TOTAL EXPECTED COSTS FOR 2 YEARS: 1st Year ----- $434,400
2nd Year ----- $364,800
TOTAL ----- $799,200
PERSONNEL | Number | Recruitment Cost / man | Mothly salary/ man | TOTAL COST/month |
Administrative | 14 | $2000 | $700 | $700 |
Technical | 9 | $200 | $300 | $300 |
Show | 35 | $6000 | $800 | $800 |
Overhead | 8 | $100 | $250 | $250 |
$240,600 Recruitment Costs
$72,850 Monthly Personnel Expenses
TOTAL PERSONNEL:
Adm. 24
Tech. 16
Show 60
Overh. 13
EXPECTED PERSONNEL COST: 3rd Year ------ $1,258,800
4th - µ Year -- $1,018,200